• Commissioning Responsibility: Overseeing the commissioning of systems and subsystems during preparation and execution phase for LNG Train Cold End and LNG Storage, ensuring they are handed over to Operations in good condition.
• Coordination: Working closely with Engineering, Contracting, Procurement, Construction, and Operations to ensure progress and achieve final RFSU (Ready for Start-Up) safely and on schedule.
• Engineering Phase: Actively participating in developing commissioning engineering deliverables and coordinating with all involved parties to prepare for pre-commissioning and commissioning activities.
• Site Supervision: Supervising commissioning at site and managing interfaces between contractors.
• Coordination for Safety and Schedule: Ensuring safe and on-schedule engineering and execution by coordinating with contractors, subcontractors, vendors, and company project departments.
• Asset Characteristics: Cold End of the Train, LNG Run-down Lines and LNG Storage.
• Supervision: No company personnel under direct supervision
Activities :
• Contract Accomplishment: Ensuring the contractor meets all contract requirements for commissioning and smooth handover of the Cold End of the Train, LNG Run-down Lines and LNG Storage to Operations.
• Preparation and Scheduling: Supervising the preparation and scheduling of pre-commissioning and commissioning activities to achieve safe and on-schedule MC (Mechanical Completion), RFSU and beyond toward RFL (Ready for Loading).
• Project Specification Compliance: Ensuring facilities are built to project specifications.
• Coordination with Operations: Coordinate witnessing of activities with operations personnel and completing remaining commissioning scope of work after hydrocarbon introduction under SIMOPS.